Construction of linear section of Ararat-Kajaran gas-main
pipeline completed
01-12-2008 21:00:00 | Armenia | Economy
YEREVAN, DECEMBER 1, NOYAN TAPAN. A ceremony dedicated to
the completion of the construction of the linear section of
186.3-km Kajaran-Ararat gas-main pipeline took place near the
city of Ararat on December 1. The indicated section is the
continuation of Iran-Armenia gas pipeline. Its construction
began in 2004 on the initiative of the Armenian government with
the aim of extending the resource base of Armenia's natural gas
supply and creating a second entry line. Kajaran-Ararat gas
pipeline was build in hard geological and weather conditions, at
an altitude of 1,500-3,000 meters above sea level.
Thanks to the implementation of more than 130 million
dollar investment program, Iranian gas will be transported to
central regions of Armenia through Kajaran-Ararat gas pipeline,
and payments for gas will be made by the principle of "gas
against electricity". Electricity generated by Yerevan Thermal
Power Plant with the capacity of 230 megawatts and the 5th power
unit of Hrazdan Thermal Power Plant with the capacity of 480
megawatts will ensure delivery of its amount envisaged by an
agreement to Iran, while the sale of "profitable" electricity
will ensure repayment of gas transportation and the program's
investments.
The ceremony was attended by the Armenian president Serzh
Sargsyan, the chairman of Gazprom OJSC's board Alexey Miller,
the former Armenian president Robert Kocharian, other officials.