YEREVAN, SEPTEMBER 29, NOYAN TAPAN. With the aim of
increasing the carrying capacity of the North Caucasus -
Transcaucasia gas pipeline, a necessity arose to replace the
500-mm pipes ensuring gas supply over the Khram River in Georgia
by 1000-mm pipes. The work is being done with funds of
ArmRusgazprom CJSC by Georgian construction organizations.
During the work, the natural gas supply of Armenia has been
temporarily cut off. Armenia's gas supply is currently ensured
from the reserves of the Abovian underground gas storage.
NT was informed by ArmRusgazprom CJSC that there are no
restrictions in the gas consumption market. The construction
work will be completed late September 29, after which the gas
supply will resume in its full volume.