WORK ON RE-EQUIPMENT OF ALAVERDI-2 SUBSTATION COMPLETED
18-12-2006 14:27:00 | Armenia | Economy
YEREVAN, DECEMBER 18, NOYAN TAPAN. The work on re-equipping
the Alaverdi-2 high-voltage substaion has been completed. The
work was done by the company Areva, the winner of an
international tender. Sahak Abrahamian, Director of the company
High-Voltage Electric Networks, told NT correspondent that KfW
Bank (Germany) has allocated 7.35 mln euros for the
implementation of the Regional System of Electricity
Transmission between Armenia and Georgia (Alaverdi-2) Program.
According to S. Abrahamian, the German bank also promised
to allocate sums for re-eqipment of two high-voltage substaions
in Gyumri.