Construction of underground car park in Liberty Square to
finish in May
25-01-2010 16:40:00 | Armenia | Economy
YEREVAN, JANUARY 25, NOYAN TAPAN. It is envisaged finishing
the construction of the underground car park in Yerevan's
Liberty Square in May of this year. After familiarizing himself
with the process of construction work, Yerevan Mayor Gagik
Beglarian said on January 23 that the car park is important for
easing traffic congestion in the city as the modern three-story
car park located under the square is designed for 500 cars.
4 billion 150 million drams will be spent on the car park's
construction. "This car park will enable to ease traffic
congestion in the city center. We also plan to build several
other car parks in Yerevan," the mayor said.
Construction work started in the 4th quarter of 2008.
According to Tiziano Ronci - Technical Director of Renco
Armestate LLC implementing construction work, the best air
conditioning, lighting, and safety systems will be installed at
the car park. There will be signboards for drivers, as well as
elevators for disabled persons. The manucipality will work out a
policy and a price-list for users of the car park. The special
computerized systems will show how many vacant parking spaces
are on each floor and how to use them. The mayor underlined that
there will be no stalls at the underground car park and truck
drivers will not allowed to park their vehicles there. It was
mentioned that after the completion of construction work, the
monuments to Hovhannes Tumanian and Alexander Spendiarian will
be put in their former places and the square will have its
previous appearance. Asphalt work will finish soon. The
installation of fire water supply pipes and the interior
decoration have been completed, and electrical equipment is
currently being installed.