CONSTRUCTION OF IRAN-ARMENIA GAS PIPELINE'S MEGHRI-KAJARAN
SECTION TO BE COMPLETED BY DECEMBER 20
24-10-2006 15:52:00 | Armenia | Economy
YEREVAN, OCTOBER 24, NOYAN TAPAN. It is envisaged to
complete the construction of the 40-km Meghri-Kajaran section of
the Iran-Armenia gas pipeline by December 20, which will allow
to start the new gas pipeline's operation ahead of the planned
date - January 1, 2007. Sahak Abrahamian, Director of
High-Voltage Electric Networks company - the customer of the gas
pipeline's Armenian secton construction, told NT correspondent
that as a result about 1.7 billion cubic meters of gas will be
imported from Iran into Armenia annually. To recap,
ArmRusgazprom company is implementing the construction work of
the Armenian side.
According to S. Abrahamian, the Armenian side received 80%
of 35 mln USD envisaged for the construction work as a loan from
Iran's Development Bank, while the remaining sum will be
allocated from own resources.
To recap, the agreement on import of natural gas from Iran
into Armenia was signed in Yerevan in May 2004. Under this
agreement, Armenia shall receive no less than 1.1 bln cubic
meters of gas from Iran annually. The term of the agreement is
20 years. Armenia will pay with electricity for the imported gas.